Marshall approves contract change on Hwy. 19 utilities

Cost hike would cover expanded design work on water, sewer lines

By Deb Gau 2 min read
Photo by Deb Gau City water and sewer lines will also be replaced in Highway 19 construction project in Marshall.

MARSHALL -- A planned 2025 construction project on College Drive in Marshall won't just affect streets and sidewalks -- there were also plans to relocate city water and sewer lines under the roadway. However, due to changes in the scope of design work on the utility lines, the city of Marshall needed to change its agreement with SRF Consulting Group.

"We've added a significant amount of work to this consultant, and they've returned and asked us for an amendment to the contract," said Marshall Public Works Director Jason Anderson. "This is a $35,108 amendment. If you combine that with the total original contract, we're at $97,706."

On Tuesday, Marshall City Council members voted to approve the contract amendment with SRF Consulting to go along with expansion of the utility project.

The Minnesota Department of Transportation plans to reconstruct part of State Highway 19 (College Drive) as it goes through Marshall. The construction project, which is planned to start in 2025, will run from the intersection of West College Drive and South Fourth Street, to the intersection of East College Drive and Bruce Street.

Anderson said SRF is also doing design work on the MnDOT project. The city hired SRF for its utility design work because it would be faster and more efficient to have one consultant working closely with both projects.

"They're already putting together the other plan sheets," he said.

City staff said the design changes SRF would need to work with included an additional length of about 1,535 feet of sanitary sewer, and an additional 3,310 feet of water main. They would also need to relocate the proposed new water main from the north side to the south side of College Drive.

The cost of the additional services was not to exceed $35,108, city staff said. Added to the original cost of the design services, the new contract maximum would be $97,706.

"At this point in time, we estimate water and sewer costs would be roughly $2.3 million. We do feel like this is a fair request from SRF, and we would recommend to move forward with this amendment," Anderson said. "We don't expect to see another change."

Anderson said the city will still be "heavily" involved in the utility project, through design and project administration.

Council members 5-2 in favor of approving the not-to-exceed amount of $35,108 for the contract amendment. Council members Steven Meister and James Lozinski cast the votes against.