Breaking News
Local News

Marshall to seek variance for chloride limits

By Deb Gau 4 min read

MARSHALL -- The city of Marshall has put a lot of work into trying to cut back on the amount of chlorides -- mostly from water softener salt -- that end up going into the Redwood River. But even after a major water softening project at the city water plant, city staff said Marshall is still having trouble meeting new limits set by the Minnesota Pollution Control Agency.

This week, members of the Marshall City Council voted to apply for a variance as the city works to reduce chloride levels in its wastewater. Wastewater facility superintendent Scott Truedson said city staff were also requesting more time to meet new discharge limits for pollutants like phosphorus and sulfates.

On Tuesday, Truedson and assistant wastewater facility superintendent Scott Przybilla gave council members an update on permit and discharge issues at the wastewater plant. Last year, the city received notification from the MPCA of more stringent limits being placed on chemicals discharged from the plant into the Redwood River.

Since then, the city has met with the MPCA, attorneys form the Minnesota Environmental Science and Economic Review Board (MESERB), and consultants with Bolton & Menk to talk about the proposed new limits, Truedson said. There were issues with a few different limits, like the new limits for chlorides, phosphorus and sulfates.

"As you know, we've been working with chlorides for almost 10 years now," Przybilla said.

A lot of the chlorides come from home water softener salt, and from local industries. Marshall Municipal Utilities recently completed a major project at its water plant to pre-soften city water, and help cut down on the use of softener salt.

While Marshall is still not meeting the new chloride limits, it has made improvements, Przybilla said.

"In 2022, even though we saw the concentration's really not lower, we've seen the mass loading -- the number of pounds (of chlorides) leaving the plant -- has gone down. And as of 2023 now to date, it's continuing to drop with the chloride reduction plan that we have in place," he said.

In 2022, Marshall also received a grant to help members of the public optimize their home water softeners, and get rebates to help replace old inefficient softeners.

When it comes to meeting the new chloride limit, Marshall won't be able to just ask for more time, Przybilla said.

"In the discussions we've had with the PCA, we requested an extension to our schedule of compliance, and they informed us that we would need to apply for a variance instead," he said. "They said they can't legally extend it because it is written in our permit that April 1, 2024, is our deadline to meet the limit."

The city isn't guaranteed to get a variance, Przybilla said. A variance would take agreement from the Environmental Protection Agency as well as the MPCA, he said. However, Pryzbila said the work the city has already done to enhance its water softening, educate the public, and help residents optimize their home water softeners helps enhance the case for a variance.

"If the city is not granted a variance, the city may have to implement more drastic measures regarding water softeners," he said.

Truedson said city staff are also requesting schedules of compliance, that would allow Marshall more time to reduce the amount of phosphorus and sulfates in its wastewater.

Truedson said the only way for the wastewater facility to meet the new sulfate limit was to reduce sulfates at their source.

"Sulfates in the groundwater in our area are high," Truedson said. "Industry in Marshall adds to our sulfate levels in the wastewater."

The city may possibly need to partner with local industries to help reduce sulfates in wastewater, he said.

Under the MPCA's new limits, Marshall would have to meet more stringent requirements on phosphorus discharged from the wastewater plant June through September, when the Redwood River has a lower flow. Przybilla said the city currently treats its wastewater with ferric chloride to help remove phosphorus, but doing that only adds to chlorides in the wastewater.

"We do have alternatives that we can use, to ferric chloride," Przybilla said. "Those have been very cost-prohibitive, but with the increases we've been seeing in our ferric costs, they're becoming more attractive. And some of them do not have a chloride contribution, and some of them we would have less of a chloride contribution with them."